This is what the new baths will look like inside
The first sod for the baths project was cut in February. Everything is to be ready in the summer of 2022.When the corona pandemic was a fact PEAB warned that there might be a risk of delays in construction because of a shortage of materials. But the problem has been solved.
– The foundation for the floor of the basement has been cast, the walls will also be cast and then work will begin on the base of the pools, says Henrik Wester, head of information at the technical department .
Now there are pictures of what the family pool and the diving pool will look like.There will be a pool for diving and one for swimming for exercise.
The diving pool will have a one-metre and a three-metre board and a five-metre tower. Another difference from the 2015 preliminary study is that there will be ten training-lanes instead of eight. The maximum cost for the baths is set at 510 million crowns, plus an extra 15 million for roads to the baths etc.