Delayed: Now Tempotorget will be demolished

The construction project has been postponed several times. Now Brinova has received the go-ahead to start demolishing.
Kristianstad • Publicerad 15 oktober 2020
Tempotorget (the Bayonet block) by Kanalgatan will be given new life, with 200 apartments among other things.
Tempotorget (the Bayonet block) by Kanalgatan will be given new life, with 200 apartments among other things.Foto: Tommy Svensson, Tommy Svensson

Tempotorget has been cordoned off.

The new residential area Bajonetten will have new shops, office space, a preschool and 200 apartments.
The new residential area Bajonetten will have new shops, office space, a preschool and 200 apartments.Foto: Lasse Ottosson

– We have started to remove furniture and inventory. We will start cleaning up and demolishing shortly, says Stina Trimark, Project Development Manager at Brinova.

Willys Hemma will remain open.
Willys Hemma will remain open.Foto: Tommy Svensson, Tommy Svensson

Decisions from various authorities have been lengthy. It has caused the delay.

– We are a few months late, says Stina Trimark.

The first phase of housing will be complete in autumn 2022.

The new preschool (in the Swedish Social Insurance Agency's old premises) will be ready by the turn of the year 2021–2022.